MaineDOT Logo

Nighttime I-195 Off-Ramps to Close This Week

Saco ? As the paving and milling project continues on I-195 in Saco, nighttime ramp closures are scheduled for Thursday, August 21st and Friday, August 22nd. The schedule is as follows:

Thursday, August 21st:

Exit 1 westbound on-ramp will be closed from 9:00 p.m. to 12:00 a.m.

Exit 1 eastbound off-ramp will be closed from 11:00 p.m. to 2:00 a.m.

Exit 1 eastbound on-ramp will be closed from 1:00 a.m. to 5:00 a.m.

Friday, August 22nd:

Exit 1 eastbound on-ramp will be closed from 9:00 p.m. to 12:00 a.m.

Martin?s Point Bridge Work To Cause Delays Monday

PORTLAND ? CPM Constructors will be placing guardrail and continue work on the northern fishing/viewing bump out on the new Martin?s Point Bridge on Monday, August 25 from 7:30 am to 4:30 pm.

This will restrict traffic to one alternating lane for that portion of the day. Travelers who want to avoid potential delays should find an alternate route on Monday morning.

The project, including full demolition and final landscaping, will be completed by the end of 2014.

Route 173 in Lincolnville to Close for 28 Days

Lincolnville ? Part of Route 173 in Lincolnville is currently closed for 28 days to replace a large culvert.

The closure will be approximately 100ft. on either side of the structure on Route 173 close to the intersection of Route 152 heading toward Searsmont (near the front of the Lincolnville telephone building).

For motorists traveling to Searsmont, detour signs will direct traffic from Route 235 to Route 105. For those traveling from Searsmont toward Lincolnville, detour signs will direct traffic onto Route 105.

Bangor I-95 Union Street Bridge Overnight Work Schedule

Bangor ? Crews will be working on Interstate 95 during the overnight hours on the Union Street Bridge project in Bangor. This work involves closing various lanes of traffic on the interstate to allow for construction to take place safely between the hours of 7:00 p.m. to 7:00 a.m. The current schedule for the week of August 25th is as follows:

Monday, August 25th:

The northbound travel lane, the southbound passing lane and the Exit 184 southbound on-ramp will be closed.

Tuesday, August 26th:

Culvert Replacement Project to Begin in Raymond

Raymond ? Crews will be replacing a culvert on Route 85 in Raymond beginning on Tuesday, August 26th at 6:00 a.m.

The project location is 0.70 of a mile north of Plains Road, or 500ft. north of Kokatosi Road. Route 85 northbound will be closed to thru traffic at Plains Road (local traffic only). For southbound motorists, traffic will be detoured at the junction with Route 11 in Casco.

An approximately nine mile signed detour route will be as follows:

I-195 Off-Ramps to Close Thursday Night **Date Correction**

Saco ? As the paving and milling project continues on I-195 in Saco, ramp closures are scheduled for Thursday evening, August 28th into Friday morning, August 29th. The schedule is as follows:

The Exit 2B eastbound off-ramp will be closed from 9:00 p.m. to 12:00 a.m.

The Exit 2A westbound off-ramp will be closed from 11:00 p.m. to 3:00 a.m.

The Exit 2B westbound off-ramp will be closed from 2:00 a.m. to 5:00 a.m.

Motorists will follow the signed detour route during these closures.

I-195 Off-Ramps to Close Thursday Night

Saco ? As the paving and milling project continues on I-195 in Saco, ramp closures are scheduled for Thursday evening, July 28th into Friday morning, July 29th. The schedule is as follows:

The Exit 2B eastbound off-ramp will be closed from 9:00 p.m. to 12:00 a.m.

The Exit 2A westbound off-ramp will be closed from 11:00 p.m. to 3:00 a.m.

The Exit 2B westbound off-ramp will be closed from 2:00 a.m. to 5:00 a.m.

Motorists will follow the signed detour route during these closures.

Culvert Replacement at the China-Winslow Town Line

China ? Crews will be replacing a failing culvert on Route 137 at the China/Winslow town line beginning on Wednesday, September 3rd.

A detour will be in place that will take motorists approximately 7.3 miles from Route 137 onto Maple Ridge Road to Stanley Hill Road to Neck Road then back to Route 137.

It is anticipated all work will be completed by the end of the day on Friday, September 5th.

This $91,000 project will be performed by KC Works, Inc. of Jackson, Maine.

Subscribe to