Construction Project Impacts - Bangor Area

The City of Bangor and the surrounding areas are going to see several construction projects over the next few years. Explore more about these projects by clicking around on the interactive map below, which is color-coded by year. If you have questions about any of these projects, use the contact form at the bottom of this page and we'll get back to you.

Click on a colored square below to expand the menu inside the map and review all associated Work Identification Numbers (WINs) within a project designation


Current Projects

""

Bangor - Broadway Bridge Replacement
 

Start Date: July 2023

Anticipated End of Construction: 2027

Scope: Bridge replacements of both northbound and southbound bridges and intersection enhancements

Impacts: Relocation of southbound traffic
 


View project page

""

Bangor - Hogan Road Diverging Diamond Interchange (DDI) Bridge Construction

Start Date: March 2026

Anticipated End of Construction: 2029

Scope: Construction of a new bridge, rehabilitation of the existing Hogan Road eastbound bridge, and removal of the Hogan Road westbound bridge

Impacts: Lane reductions or alternating traffic

View project page

Construction of the stillwater ave bridge

Oldtown - Stillwater Ave. Bridge Replacement

Start Date: May 2025

Anticipated End of Construction: 2028

Scope: Replacement project for the two Llewllyn Estes Bridges and improve the Bennoch Road (Route 16) and College Avenue (Route 2A) intersections

Impacts: Lane Restrictions
 

View project page

Upcoming Projects

Bangor - Broadway and Stillwater Ave

Estimated Start: 2026

Anticipated End of Construction: Fall 2026

Scope: Intersection improvements w/ signal

Impacts: One lane work zone (500') along a corner, with maintaining two-way traffic.

Bangor - Hancock Street

Estimated Start: 2026

Anticipated End of Construction: Fall 2026

Scope: Paving

Impacts: Intermittent lane closures, with alternating one-way traffic, to facilitate paving operations

Bangor - Route 2

Estimated Start: 2026

Anticipated End of Construction: Fall 2026

Scope: Paving

Impacts: Intermittent lane closures with alternating one-way traffic to facilitate paving operations

Bangor / Brewer - Penobscot Bridge

Estimated Start: Spring 2027

Anticipated End of Construction: Fall 2027

Scope: Bridge Wearing Surface Replacement

Impacts: Bridge reduced to only two lanes of traffic

Bangor / Brewer Joshua Chamberlain Bridge 

Estimated Start: Spring 2026

Anticipated End of Construction: Fall 2026

Scope: Bridge Wearing Surface Replacement

Impacts: Only one traffic lane headed westbound

Bangor / Orono - Stillwater Avenue

Estimated Start: Summer 2026

Anticipated End of Construction: Fall 2026

Scope: Milling and Light capital paving 

Impacts: Intermittent lane closures with alternating one-way traffic to facilitate paving operations

Brewer - North Main Street and State Street

Estimated Start: Summer 2026

Anticipated End of Construction: Fall 2026

Scope: Intersection Improvements w/ Signal

Impacts: Intermittent lane closure and occasional detour

Future Projects

2027

  • Kenduskeag Avenue Bridge - Bridge Replacement
  • Penobscot River Bridge - Wearing Surface and Substructure Repair

2028 and beyond

  • Bangor / Brewer I-395 Bridge Project: 2028
  • Bangor Stillwater Ave - Traffic Light Installation / Replacement: 2028
  • Bangor State Street - Safety Improvements: TBD
  • Brewer Parkway South and Pendleton Street - Safety Improvements: TBD