Ticonic Bridge Schedule

  • March 2023 Begin Construction
  • Late-August/early September 2023 Detour Westbound Traffic over Carter Memorial Bridge while Eastbound stays on the Existing Bridge
  • Early September 2023 Detour pedestrians to 2 Cent Bridge
  • November 2024 Detour Eastbound and Westbound Traffic over Carter Memorial Bridge (full bridge closure, no traffic EB or WB on Ticonic Bridge)
  • April 2025 go back to Eastbound Traffic and Pedestrians on Ticonic bridge while Westbound Traffic remains detoured over Carter Memorial Bridge
  • September 2026 Open both Eastbound and Westbound Traffic on the New Bridge.
  • May 2027 Construction Complete