Windham Route 302 Reconstruction - Schedule and Documents

Additional Resources

Federal Highway Administration (FHWA). (n.d.).  Proven Safety Countermeasures - Reduced Left Turn Conflict Intersections

FHWA. (2024, July 25). Intersection Safety - Research and Education Resources

Gayah, Vikash V. (2021, June 6). Housing and Urban Issues - Sick of Dangerous City Traffic? Remove Left Turns. Governing.

Completed Project Milestones

  • Draft Horizontal Vertical Alignment- June 4th, 2024
  • Final Horizontal Vertical Alignment - November 2024
  • Draft Preliminary Design Report - September 2025
  • Final Preliminary Design/Draft Plans Impact Complete Report - February 2026
  • Final Public Hearing - August 12, 2026
  • Plan Impact Complete - September 2026

Upcoming Project Milestones

  • Plans, Specifications, Estimate Complete - June/July 2027
  • Project Advertise - August 2027
  • Construction Begin - January 2028
  • Construction Complete - July 2031

Detailed Sections of the plan sets

Public Meeting - August 12, 2026

Concurrent Virtual Meeting ( comment period Sept 2 - 16, 2026

Open House - June 18th, 2025

Preliminary Public Hearing- June 4th, 2024