Route 196 Paving Work in Topsham

TOPSHAM - The Maine Department of Transportation will be doing paving work on part of Route 196 in Topsham. The work area begins just south of the Brunswick town line and extends north for almost two miles to Route 201 in Topsham. This project includes paving work on the Merrymeeting Bay Bridge. Work is scheduled to begin on Tuesday, July 6th and be completed on Friday, July 23rd. Drivers should expect overnight lane closures between the hours of 8:00 p.m. and 6:00 a.m. The contractor on this project is All States Asphalt of Richmond. The contract amount is $664,459.