MaineDOT Extends Detour for Puddle Dock Bridge in Fort Fairfield
FORT FAIRFIELD – November 20, 2026 — The Maine Department of Transportation (MaineDOT) has extended the detour for the bridge replacement project of the Puddle Dock Bridge over Pattee Brook on Route 161 (Main Street) between Fort Hill Street and Dorsey Road in Fort Fairfield.
The project work includes replacing the bridge with new abutments and composite precast superstructure.
During the project, a temporary detour with alternating single lane traffic will be implemented. Traffic will be restricted to one 11' lane of alternating traffic.
The original detour that was scheduled to end in Fall 2026 has now been extended to January 2027. The bridge will be opened temporarily in January to help with winter maintenance. In spring 2027, the bridge will be closed again, and traffic will be put back on the temporary detour to allow for the approach work for the new bridge to be completed.
Motorists should expect delays and use caution when traveling through the detour zone.
Work is expected to be completed by summer 2027.
The contractor for this project is Devoe Construction of Eagle Lake, Maine.
The contract amount is $3,694,000.