I-195 On and Off-Ramps to be Paved Overnight

Saco ? As the paving project continues on I-195 in Saco, ramp closures are scheduled for next week beginning Sunday, September 28th. The schedule for the week is as follows:

Sunday, September 28th:

The Exit 1 westbound off-ramp will be closed from 9:00 p.m. to 2:00 a.m.

The Exit 1 westbound on-ramp will be closed from 12:00 a.m. to 5:00 a.m.

Monday, September 29th:

The Exit 2A westbound off-ramp will be closed from 9:00 p.m. to 2:00 a.m.

The Exit 2A westbound on-ramp will be closed from 12:00 a.m. to 5:00 a.m.

Tuesday, September 30th:

The Exit 2B westbound off-ramp will be closed from 9:00 p.m. to 5:00 a.m.

Motorists will follow the signed detour routes during these closures.