Bangor – Brewer I-395 Bridges

The project includes the design and construction of three bridge replacements and three bridge rehabilitations along the I-395 corridor between Bangor and Brewer, beginning near Exit 3 and ending near the Green Point Road Bridge. The six bridges include I-395 over Main Street in Bangor, Veterans Remembrance Bridge over the Penobscot River, I-395 over MCRR in Brewer, Robertson Blvd over I-395 in Brewer, Parkway South over I-395 in Brewer, and Green Point Road over I-395 in Brewer.

Project Documents

RFSO Files

Revised Bangor-Brewer I-395 Bridges RFSOI (PDF) 

(Revised Construction Completion Date June 30, 2032)

Appendix A - Proposers General Information Form (PDF)

Appendix E - Civil Rights Supplemental and EEO Fillable Form (PDF)

Draft RFP Files

Request for Proposal Book 1 - Design Build Low Bid General Conditions DRAFT (PDF)

Request for Proposal Book 2 - Project Requirements DRAFT (PDF)

Bangor-Brewer I-395 Responses to Draft RFP Questions (PDF)

Final RFP

Request for Proposal Book 1 - Design Builder Low Bid General Conditions FINAL (PDF)

Request for Proposal Book 2 - Project Requirements FINAL (PDF)

Appendix A - Federal Wage Rates

Federal Wage Rates (zip)

Appendix B - Contract Forms and Exhibits

Contract Forms and Exhibits (zip)

Concept Plans (zip)

Appendix D - Existing Plans and Inspection Documents

Existing Plans and Inspection Documents Part 1 (zip)

Existing Plans and Inspection Documents Part 2 (zip)

Existing Plans and Inspection Documents Part 3 (zip)

Existing Plans and Inspection Documents Part 4 (zip)

Existing Plans and Inspection Documents Part 5 (zip)

Existing Plans and Inspection Documents Part 6 (zip)

Existing Plans and Inspection Documents Part 7 (zip)

Existing Plans and Inspection Documents Part 8 (zip)

Existing Plans and Inspection Documents Part 9 (zip)

Existing Plans and Inspection Documents Part 10 (zip)

Existing Plans and Inspection Documents Part 11 (zip)

Existing Plans and Inspection Documents Part 12 (zip)

Existing Plans and Inspection Documents Part 13 (zip)

Existing Plans and Inspection Documents Part 14 (zip)

Existing Plans and Inspection Documents Part 15 (zip)

Existing Plans and Inspection Documents Part 16 (zip)

Existing Plans and Inspection Documents Part 17 (zip)

Existing Plans and Inspection Documents Part 18 (zip)

Existing Plans and Inspection Documents Part 19 (zip)

Existing Plans and Inspection Documents Part 20 (zip)

Appendix E - Geotechnical Data

Geotechnical Data Part 1 (zip)

Geotechnical Data Part 2 (zip)

Geotechnical Data Part 3 (zip)

Appendix F - Traffic and Accident Data

Traffic and Accident Data (zip)

Appendix G - Survey Data, Wetlands Delineation, and Existing Alignments

Survey Data, Wetlands Delineation and Existing Alignments (zip)

Appendix H - Permits and other Environmental Information

Permits and other Environmental Information (zip)

Appendix I - Supplemental Specifications and Special Provisions

Supplemental Specifications and Special Provisions - August 17, 2026 (zip)

Appendix J - Utilities

Utilities (zip)

Current Schedule

DateEvent
3/04/2026MaineDOT Issues RFSOI
3/18/26 at 3:00 PM ESTDeadline for Design-Builders to Submit Questions on RFSOI
4/01/2026MaineDOT Issues Responses to Questions Received on the RFSOI
4/14/2026 at 3:00 PM EDTDeadline for Design-Builders to Submit SOI
4/22/2026MaineDOT Issues Notification of SOI Responsiveness to Design-Builders
4/29/2026Deadline for Design-Builders to Submit Cure for SOI Responsiveness (If Applicable)
5/13/2026MaineDOT Evaluates and Ranks SOIs and Notifies Design-Builders of Selection Results
6/03/2026MaineDOT Issues Draft RFP
7/02/2026 at 3:00 PM EDTDeadline for Design-Builders to submit Questions on the Draft RFP
7/17/2026MaineDOT Issues Responses to Draft RFP Questions
8/17/2026MaineDOT Issues Final RFP
One meeting per team between 9/21 and 9/30/2026.Design-Builders Attend One-On-One Meetings with MaineDOT (If applicable)
10/21/2026 at 3:00 PM EDTDeadline for Design-Builders to Submit ATC Proposals
11/17/2026MaineDOT Issues Responses to ATC Proposals
12/09/2026 at 3:00 PM EDTDeadline for Design-Builders to Submit Questions Final RFP
12/30/2026MaineDOT Issues Responses to Final RFP Questions
1/29/2027at 3:00 PM EDTDeadline for Design-Builders to Submit Technical Packages
2/17/2027MaineDOT Issues Notification of Technical Proposal Responsiveness to Design-Builders
2/26/2027Deadline for Design-Builders to Submit Cure for Technical Responsiveness (If Applicable) and Price Proposal
3/17/2027 at 11:00 AM EDTDeadline for Design-Builders to Submit Proposal Guaranty Package
3/17/2027 at 11:00 AM EDTMaineDOT Opens Price Proposals
Spring 2027MaineDOT Awards Contract
Spring 2027Design-Builder Begins Final Design & Construction
6/30/2032Design-Builder Completes Final Design & Construction