WIN(s): 024513.00
Advertised Date:
Municipality: Fryeburg / Lovell
Summary:
Cyclical Pavement Resurfacing and Safety Improvements:
- Located on Route 15 in Fryeburg beginning at Bog Pond Road and extending north 2.57 miles.
- Beginning 0.22 of a mile north of Summit Drive and extending north 2.53 miles.
- Beginning at Eastman Hill Road and extending north 4.75 miles.
Bid Date:
Documents
Plan Holder List Registration
Plan Holder List Registration:
RFI - Request for Information
RFI - Request for Information:
Awarded to
All States Asphalt Inc. of Sunderland, MA
Date Awarded
Status